Extension of time fees are calculated based on the land rates issued by the ACT Revenue Office for the block.
- For breaches between 1 February 1993 and 30 March 2008, fees are calculated quarterly.
- For breaches between 31 March 2008 and 21 June 2012, fees are calculated against the land rates for the block using a multiplier of 1 x the rates for the first year up to 5 x the rates for the fifth year.
- For breaches between 22 June 2012 and 31 March 2014, fees are calculated at 0.01 in the first four years and then at 5 times the rates in the fifth year.
- For Crown leases issued after 1 April 2014, fees are calculated at 0 in the first four years and at 1 x the rates in the fifth year.
Fees are calculated from the previous multipliers used – for example, if the previous extension were calculated into the third year, any new extension calculation will begin in the third year until the fifth year is reached.