You must only send the information required when you respond to a request for further information. You don't need to send any other documents unless requested.

If you receive a request for further information, you won't be charged an extra fee.

If you change your application after a request for further information, you'll need to submit a DA amendment. A DA amendment also applies if you send more information than requested.

DA amendments are only able to be made where the amended development:

  • is substantially the same as what was originally proposed, and
  • is not for a significant development – when the original application wasn't a significant development.

DA amendments will attract an additional fee.