An Exemption Declaration is a type of planning approval.

An exemption declaration may be available where a development would otherwise qualify as exempt development but has a minor departure from one or more applicable exempt development requirements.

To issue an exemption declaration, the Territory Planning Authority must be satisfied that:

  • the non-compliance is minor
  • the proposal will not have an unreasonable impact on neighbouring properties or occupiers
  • the proposal will not result in more than minor environmental impacts
  • any additional shadowing of neighbouring homes or private open space will be minor
  • any required neighbour notification has been completed.

Development Controls

Development controls set out the planning requirements that development must meet to qualify as exempt development under the Planning (Exempt Development) Regulation 2023.

For single dwelling housing, these requirements cover matters such as:

  • building setbacks
  • building and solar envelopes
  • private open space
  • courtyard walls
  • parking
  • other design and siting requirements

There are development controls that apply across the ACT, as well as district-specific controls that apply to particular suburbs and estates. Which controls apply will depend on the location of your property and the type of development proposed. All relevant controls must be complied with for a proposal to qualify as exempt development

Mandatory Matters Development Controls

Some planning requirements are classified as mandatory matters. These are key planning requirements that must always be complied with and cannot be varied through an exemption declaration.

For single dwelling housing, mandatory matters include:

  • building height
  • number of storeys
  • site coverage

If a proposal does not comply with a mandatory matter, it cannot be approved through the exemption declaration process and may require a Development Application.

The Mandatory Matters Development Control commences on 1 January 2027.

Eligibility

An exemption declaration can be considered where the non-compliance is minor and undertaking the works wouldn’t result in significant impacts in certain areas..

From 1 January 2027, an exemption declaration for a single dwelling can be considered for any control in the Single Dwelling Housing Development Control, available on the Development Control webpage. This includes controls like:

  • front, side or rear setback requirements
  • building envelope requirements
  • solar building envelope requirements
  • private open space dimension requirements
  • principal private open space dimension requirements
  • courtyard wall setback requirements.

Other types of exempt development, like those outlined on Check if you need a DA are also eligible for an exemption declaration.

The guidance below outlines the types of departures that will generally not be considered minor for the purposes of an exemption declaration.

Ineligible Departures

Applications cannot be considered where they involve:

Where a proposal does not comply with the exemption criteria and does not meet the eligibility for an exemption declaration, the proposal will generally need to be amended or assessed through a Development Application.

Note: An exemption declaration is intended to address a minor non-compliance only. All other applicable requirements for exempt development must still be met. If a proposal does not comply with multiple requirements, or the non-compliance is more than minor, an exemption declaration may not be available.

What you need to apply

You must include the following documents with your exemption declaration application. All relevant plans and supporting documents should be uploaded as a single PDF wherever possible:

  • An online application form including details of the proposed departure(s) and the relevant development control provisions
  • A letter of authorisation [255.5 KB] signed by the lessee(s) of the land and the applicant
  • A complete set of plans that clearly identify the departure(s), including dimensions and the extent of the non-compliance:
    • site plan showing any setback or private open space departures
    • floor plans showing any setback or private open space departures
    • elevation and section plans showing any building envelope or solar building envelope departures

    Note: Relevant plans should identify the departure(s) only and clearly show the extent of the non-compliance, including any encroachments, reduced setbacks or building envelope departures. Dimensions and areas of non-compliance should be clearly labelled on the plans.

  • Shadow diagrams for any solar building envelope departure, including shadows at 9am, 12pm and 3pm on the winter solstice and the extent of any additional shadowing
  • Evidence that any required neighbour notification has been completed in accordance with section 1.18 of the Planning (Exempt Development) Regulation 2023. This may include a completed summary of written information to adjoining resident form [308.3 KB] or other documentation demonstrating that the required information has been provided to adjoining occupiers
  • Any additional information relied on to support the application, including photographs, supporting statements or letters of support

It is recommended that the application clearly explain:

  • the relevant requirement that is not being met
  • the extent of the non-compliance
  • why the departure is considered minor, referring to the provisions of the Planning (Exempt Development) Regulation 2023 wherever possible.
Dimensioning diagrams examples

Envelope departure – height

Example of how solar building envelope departures are to be displayed when lodging an exemption declaration.

Envelope departure – length

Example of how solar building envelope departures are to be displayed when lodging an exemption declaration.

Setback departure - angled to boundary

Example of how setback departures are to be displayed when lodging an exemption declaration.

Setback departure - square to boundary

Example of how setback departures are to be displayed when lodging an exemption declaration.

POS departure

Example of how departures from private open space are to be displayed when lodging an exemption declaration.

Courtyard wall departure

Example of how setback departures associated with courtyard walls are to be displayed when lodging an exemption declaration.

Shadow diagram - extended shadow

Example of a shadow diagram that displays departures from solar building envelopes to be lodged with an exemption declaration.

Consulting your neighbours

Before submitting an exemption declaration application, you may be required to provide information about your proposal to adjoining occupiers. This generally applies to compliant single dwelling development and certain demolition proposals.

The required information must include:

  • a completed Information for adjoining resident form [182.3 KB]
  • site plans and elevation plans for the proposal
  • shadow diagrams where the proposal involves an encroachment beyond the solar building envelope
  • any additional information required by the Territory Planning Authority.

Neighbour Support

You are not required to obtain support from adjoining occupiers to lodge an exemption declaration application. However, written support may assist the Territory Planning Authority when considering proposals that involve departures from solar building envelope requirements.

If an adjoining occupier wishes to support a proposal, they should provide a signed statement confirming that they have reviewed the plans and support the proposed departure. The statement should include their name, address and contact details.

Your neighbours can use the below as a guide:

"I/We (insert full name/s of neighbour/s),

owner/s of (full address of neighbour/s),

have viewed the proposed plans (insert revision number)

dated (insert date revised plans were drawn)

for (full address of block subject to application)

and support the departure/s (list if you wish) proposed."

If you seek your neighbour's support, they must sign and date the letter and plans with their full names and contact details.

Contacting Adjoining Occupiers

The Territory Planning Authority cannot provide contact details for adjoining occupiers.

If required, you may be able to identify adjoining property owners through:

  • a title search on the ACT Land Information System
  • the builder or site representative (where construction is underway)
  • the estate developer.

Checklist Before You Apply

To avoid delays or the need to submit a new application, ensure your application includes all relevant information at the time of lodgement.

Before lodging your application, check that you have:

  • completed the online application form.
  • included a letter of authorisation [255.5 KB] signed by the lessee(s).
  • clearly identified:
    • the provision(s) you are seeking a departure from; and
    • the extent of the departure (including dimensions and areas of non-compliance where relevant).
  • included plans showing all proposed departures.
  • shown departures only on the relevant drawings:
    • site plans for setbacks and open space departures
    • floor plans for setbacks and open space departures
    • elevations and sections for building envelope and solar envelope departures.
  • clearly labelled and dimensioned each departure on the plans.
  • included shadow diagrams for all solar building envelope departures.
  • provided evidence that any required neighbour notification has been completed, including a completed Summary of Written Information to Adjoining Resident Form [182.3 KB] (where applicable).
  • included any supporting material that assists in demonstrating that the departure is minor, such as:
    • photographs
    • supporting statements
    • neighbourhood context plans; or
    • letters of support from adjoining occupiers.
  • consider obtaining support from affected neighbours where the application involves solar building envelope or similar departures that may affect neighbouring properties.
  • had the proposal reviewed by a building certifier or suitably qualified professional to confirm that:
    • all relevant departures have been identified; and
    • all other applicable planning requirements are met.

Note: The most common cause of delays is failing to clearly identify all departures and provide sufficient information to demonstrate why they should be considered minor. A complete and accurate application will assist the Territory Planning Authority to decide within the statutory timeframe

How to apply

Lodge your application online.

Fees

There is a flat fee to apply for exemption declarations, charged on application. Find out about fees and charges.

Assessment and processing

Exemption declaration applications are assessed on a case-by-case basis against the eligibility criteria. The Territory Planning Authority will assess the proposal as submitted and will not recommend design changes or amendments to make a proposal eligible for an exemption declaration. If a departure is not considered minor, the application may be refused.

Following assessment, the Territory Planning Authority will either:

  • issue an exemption declaration; or
  • refuse the application.

Timeframe

The Territory Planning Authority must decide an exemption declaration application within 10 working days.

Where further information is requested, the statutory assessment period pauses until the requested information is received.

Further Information Requests

The exemption declaration process is intended to be a streamlined assessment pathway for proposals involving minor non-compliance. It is designed to provide timely decisions and is not intended to operate like a Development Application process.

The Territory Planning Authority may request further information where minor clarification or additional supporting material is required to complete an assessment. However, further information requests are not a formal part of exemption declarations and these should not be relied on to facilitate design changes or amendments to a proposal.

Applicants should ensure all relevant departures, plans, supporting information and evidence are provided at the time of lodgement to avoid delays and reduce the risk of refusal

After you apply

Amending an application

There is no process to amend exemption declarations. This means that you must include all relevant encroachments in your initial application. You will need to submit a new application for any more encroachments.

Appealing a decision

Exemption declaration decisions are final. If approved, you can proceed to develop your block under the approval issued. An approved exemption declaration will last for a period of 3 years. Further time may be allowed if provided in writing by the Territory Planning Authority.

Under the legislation, you won’t be able to review or appeal the decision to the ACT Civil and Administrative Tribunal (ACAT). If you want to challenge a decision, you will need to seek independent legal advice.

If your application for exemption declaration is refused, you’ll need to either: