An application for an Environmental Impact Statement (EIS) exemption was lodged under section 211B of the Planning and Development Act 2007 for the relocation of 132kV transmission lines in the Molonglo Valley.

The proposal will replace the existing overhead 132kV electricity transmission line with new underground electricity transmission lines and includes associated works. The new underground cables will follow a new alignment connecting to the existing grid at the east of Kama Nature Reserve and near Tuggeranong Parkway. This new alignment minimises impact on future urban development in the Molonglo Stage 3 Future Urban Area.

This EIS exemption application was lodged concurrently with a development application (DA-201936352).

Overview of EIS exemptions

Section 211 of the Planning and Development Act 2007 allows for a proponent to seek exemption from the requirement to complete an Environmental Impact Statement. The Minister has discretion under this section to grant an exemption if satisfied that previous studies have adequately identified the potential environmental impacts of the proposal.

A proponent may apply for an EIS exemption for any proposal that would trigger an EIS under Schedule 4 of the Planning and Development Act 2007.

Public consultation

The EIS exemption application was open for public comment for 35 working days with the comment period ending on 10 June 2020.

Current status: EIS Exemption process complete

On 13 April 2021, the Minister for Planning and Land Management granted an EIS exemption for the Molonglo 132kV Transmission Line Relocation.

The concurrent development application (DA201936352) will now be assessed and decided on by the Planning and Land Authority.

Application and supporting documents